Apex Manufacturing was running a 15-year-old .NET Framework 3.5 ERP on ageing on-premise hardware. The system suffered frequent downtime (avg. 4 hrs/month), could not scale during month-end peaks, and had no disaster recovery capability. Hardware refresh would cost ₹2.5 Cr — and not solve the scalability problem.
VFL Technologies conducted a 2-week Azure Migration Assessment, then executed a phased lift-and-refactor migration. We migrated the SQL Server 2008 database to Azure SQL Managed Instance using DMS in continuous sync mode, modernized the .NET 3.5 application to .NET 8, containerized services with Docker, and deployed to Azure Kubernetes Service with auto-scaling.
Azure Migrate assessment, dependency mapping, TCO analysis, and risk matrix.
Target architecture design, network topology, security controls, and migration runbook.
.NET 3.5 to .NET 8 upgrade, Dockerization, and SQL 2008 compatibility fixes.
Azure landing zone, AKS cluster, SQL MI, and Azure DevOps pipelines via Bicep.
DMS continuous sync, data validation, and parallel run period.
45-minute cutover window, post-migration monitoring, and performance tuning.
"VFL Technologies delivered beyond expectations. The migration was flawless — our users didn't even notice the cutover. And now our ERP is faster than ever."